兴平市中心大街转盘改造、迎宾大道提升改造最新进展...


            <p>中心大街转盘改造工程:</p><section><section powered-by="xiumi.us"><section><section><section><section>转盘内透层油、封层已喷洒、铺设完毕,底油铺设中。</section><section><br></section><section>迎宾大道提升改造工程:</section></section></section></section></section><section powered-by="xiumi.us"><section><section><section powered-by="xiumi.us"><section><div style="text-align:center"></div></section><section>迎宾大道提升改造工程:乔、灌木栽植已全部完成;地被植物栽植完成32000㎡,道路两侧绿化带及人行道道牙石完成9000m;人行道透水混凝土完成4500㎡;整体工程已完成总工程量的85%。</section></section><section powered-by="xiumi.us"><section><section><section powered-by="xiumi.us"><section><div style="text-align:center"></div></section><section><br></section></section><section powered-by="xiumi.us"><p><div style="text-align:center"></div></p><p>图片、资料由园林处、城建科提供</p><p>来源:兴平市住房和城乡建设局<br></p></section></section></section></section></section></section></section></section><p><br></p><p><br></p>
         